PTiller

Disaster Recovery Plan - scenario is the entire Production Data center is offline.

Discussion created by PTiller on Sep 30, 2014
Latest reply on Sep 30, 2014 by Jennifer_Jinhong_34

The plan is that we will have a backed up copy of the production database in Green Bay where our DEV environment is currently.

We restore the database and change the ODBC setting in DEV to point to the Production copy.

All that is pretty easy, but – for our applications the plan is to utilize the DEV agents in Green Bay for running what are now Production jobs. I can see that is going to be a problem with them having the system name in their INI file listed as NON_PROD – would it be easy enough to just rename the DR_PROD system as NON_PROD so the agents can connect and get the license vs having to change each agents INI file?

Outcomes