We are repeatedly experiencing issues with generating accurate forecasts in AE. We have 2 issues

1) We are scheduling an automatic recalculation to run on a daily basis of the forecast and because we have many many C_Period jobs it takes a long time to calculate additionally it fails typically on the forecast of a scheduler object.
2) When we do successfully extract the data it is not in a usable format. What we would like to be able to do is extract a list for a designated day and be able to illustrate this in a format that our technical support are able to analyse easily. We would like to see the information in the following format - workflow which would include jobs/start time/run time and any related dependencies.