Here is the scenario.

 

  1. A generic role PM is added to the project
  2. A requisition is created for the for the PM role
  3. The resource is proposed for the requisition 
  4. Booking status is 'Soft' and 'Request status' is 'Proposed'

 

Team->Detail showing the planned allocation for the PM role.  

 

From Requisition->Resources->Resource allocation page does not the "SOFT" allocation details

 

How the BM/RM will find out the soft allocation of all named resources when the requisition is in 'Proposed' status?

 

Note:  The allocation details of the named resource shows only when the resource is "Hard" booked.

 

Any thoughts/pointer is greatly appreciated

 

Thanks

-Venkitta