How Does Clarity Calculate Overall Project Status Color

Question asked by calth02 on Aug 26, 2011
Latest reply on Mar 22, 2012 by aprilso
Can someone tell me where I can find specific information on how Clarity calculates the overal project status color. I know it is driven off of the indicators on the Schedule page. I know this:

-all green = green overall
-one red = red overall
-one yellow = yellow overall

but

does two yellows = red?
does three?
four?

Is there specific weighting or is is simply driven off the colors?

Thanks,

Tom