Transfer of Actuals / Transactions

Question asked by navzjoshi00 Champion on Sep 2, 2011
Latest reply on Sep 26, 2011 by Chris_Hackett
Scenario -

There are 2 projects - A & B. We need to transfer the actuals (26 hrs - filled for the month of April) / transactions from project A to B for a resource R

We did the following -

Created 6 -ve voucher transactions on project A (totalling 26 Hrs - for the date Aug 10, 2011), and 1 +ve transaction of 26 Hrs on project B (for the date Aug 10, 2011).

What we now see is that 26 hours are posted on project B for August (visible for Aug 2011).

However, the 26 hours on project A are still visible on Team > Detail. Also, on the dashboard tab of project A, the actuals are still visible, and they cannot be seen on the dashboard tab of project B

Am I missing something here ?

A quick response would be much appreciated.

NJ