AnsweredAssumed Answered

Shifting Allocations

Question asked by clayton.reynolds_01 on Jan 24, 2012
Latest reply on Jan 26, 2012 by another_martink
Clarity v12.1.1.1

Is anyone aware of a way to shift allocations of an entire team by a certain amount of days?

Example:
Idea investment start and finish dates are 4/1/2012 to 4/30/2012

3 Roles are on the Idea Team page with following start and finish dates:

BA 4/1-4/8

Developer 4/1/-4/30

DBA -4/23-4/30

I would like to Shift Allocations by ~60 days so that dates are as follows:

BA 6/1-6/8

Developer 6/1/-6/30

DBA -6/23-6/30

There doesn’t seem to be a way of doing this in[b] one step (and changing Investment start and finish dates doesn’t do it.)

Outcomes