Stagger work over duration of task

Question asked by bfarquhar on Jun 27, 2012
Latest reply on Jul 9, 2012 by another_martink
I'm hoping someone can tell me how I cna do the following.... I have a task that lasts 3 weeks and has 40 hours of ETC. I have 1 resource assigned to the task. I want that resource to work 20 hours in the first week, Zero hours in the second week and 20 hours in the last week. How would I set that up ? Currently it is distibutting the time evenly (13.33 hrs) across each of the 3 weeks. Any help would be greatly appreciated.
Thanks,
Ben