Problem with the new (13.1) Top-Down Planning Portlet

Question asked by BarakBes on Nov 21, 2012
Latest reply on Nov 27, 2012 by navzjoshi00
Hi,

I have looked into the new portlet released to version 13.1 calld Top-Down Planning by Investment. It is part of resource planning, in a new tab called "Top Down Planning". I have a demo data-set.
I have a problem with the "Total Capacity" row. I compare it to the "Role Capacity" portlet and I expect that when filtered the same - they will give me the same Total capacity. However - the capacity in top-down planning is much larger (e.g. 169 compared to 66).
I counted the actual number of resources and found out that the number for "Role Capacity" is right.

Moreover, capacity (not allocation) shouldn't change if I look at approved projects, not approved projects or all. However, in the "Top Down Planning" I get a capacity of 149 for approved prjects, 20 for non-approved and 169 for all.

Reagrds,
Barak